Phase 02 of 08

Design & Engineering

Turning the production requirement into buildable drawings, calculations, and specifications.

Typical duration
4–12 weeks
Industrial roof structure with skylights, photographed from below in black and white

Phase 02 in short

Design and engineering produces the documents every later stage depends on. We start with basic design and FEED to lock the big moves, then move into detailed engineering across architecture, structure, and MEP. Structural calculations follow the applicable SNI codes, and all disciplines are coordinated in a single model so that clashes between pipework, ducting, and structure are found on screen rather than on site. A design error that reaches construction costs several times more to fix, which is why this phase is not compressed on request.

What we do

  1. Basic design and FEED: locking the structural concept, span module, clear height, and utility zoning.

  2. Architectural detailed design: plans, sections, elevations, details, and material schedules.

  3. Structural detailed design with calculations to SNI 1727 for loading, SNI 1726 for seismic, SNI 2847 for concrete, and SNI 1729 for steel.

  4. Mechanical, electrical, and plumbing detailed design including electrical load, cooling load, and water demand calculations.

  5. BIM modelling and cross-discipline clash detection before drawings are released to site.

  6. Technical specifications and works requirements for materials and equipment.

  7. Bill of quantities and class 2 cost estimate at roughly ±10 per cent accuracy.

  8. Value engineering: finding savings that do not reduce capacity or building life.

What you receive

  • Complete detailed drawings: architecture, structure, MEP
  • Structural calculation report, signed by the responsible engineer
  • Technical specifications and works requirements
  • Bill of quantities and class 2 cost estimate
  • Coordinated BIM model and clash report
  • Value engineering proposals with their cost impact
Codes and references
Loading SNI 1727:2020
Seismic SNI 1726:2019
Concrete SNI 2847:2019
Steel SNI 1729:2020
Estimate accuracy ±10% (class 2)
Typical duration 4–12 weeks

Questions about this phase

Can TCC continue a design started by another consultant?
Yes. We first run a design review over the structural calculations, MEP capacity, and drawing completeness, then issue the findings in writing before taking on responsibility. We do not sign off on a design we have not checked.
Is BIM really needed for a simple factory?
For a simple clear-span warehouse, often not. For a plant with process ducting, dust collection, compressed air, and a dense pipe rack, a coordinated model is almost always cheaper than dismantling clashing installations on site.

Tell us about the project.

Send the outline: location, approximate area, process type, and target production start. We will come back with the questions that need answering before any number means anything.